• Draw the following network using Precedence Diagram Method and determine the PDMin; Total Float; and draw the Bar-chart considering the contract duration = 30 days with the following data:
Activity Depends on Duration (days)
A — 3
B — 4
C A 3
D A 4
E B 8
F A, B 3
G B 6
H D, G 7
I F 2
J H, I 10