A Project Charter and a Statement of Work for the Future Technology Data Center
Project Timeline (First-Cut):
- Project Start: April 15, 2024
- Project End: September 15, 2024 (estimated)
- Key Milestones (to be further defined in the project plan):
- New site infrastructure readiness
- Disaster recovery site testing
- Parallel operation phase
- Final cutover
- Decommissioning
5. Project Budget (First-Cut):
- $90,000 - $100,000 (inclusive of new site infrastructure upgrade)
6. Project Team:
- Charles Parker (Project Manager)
- [Team Member Name] (Facilities Representative)
- [Team Member Name] (Operations/Systems Representative)
- [Team Member Name] (Operations/Telecommunications Representative)
- [Team Member Name] (Systems & Applications Representative)
- [Team Member Name] (Customer Service Representative)
7. Assumptions:
- The remote disaster recovery "hot" site is fully functional and capable of handling 100% of FT's client load.
- Necessary permits and approvals for the new site are obtained in a timely manner.
- Key vendors and contractors are available as needed.
8. Risks:
- Potential delays in infrastructure readiness at the new site.
- Unexpected issues during the parallel operation phase.
- Difficulties in coordinating with the disaster recovery site.
9. Approvals:
Marion Hassing, VP of Operations
Statement of Work: Future Technology Data Center Relocation
Project Name: FT Data Center Relocation
1. Introduction:
Future Technology (FT) requires the relocation of its data center to a new facility at Mobile International Airport Industrial Complex. This Statement of Work (SOW) outlines the scope of work, deliverables, timelines, and responsibilities for the project.
2. Project Objectives:
- Relocate the data center without any downtime for FT's 315 clients.
- Ensure a seamless transition by leveraging the remote disaster recovery "hot" site.
- Complete the project within four to five months and within the allocated budget.
3. Scope of Work:
The project includes the following tasks:
- Planning & Preparation:
- Detailed project planning, including a comprehensive timeline, resource allocation, and risk management plan.
- Coordination with the new facility for infrastructure readiness (power, cooling, network connectivity).
- Thorough testing and validation of the disaster recovery site's ability to handle full client load.
- Relocation Execution:
- Physical relocation of all servers, storage devices, network equipment, and other hardware to the new data center.
- Installation and configuration of all systems at the new location.
- Implementation of the parallel operation phase, where both the old and new data centers operate simultaneously.
- Regular monitoring and testing during the parallel phase to ensure stability and performance.
- Cutover & Decommissioning:
- Planned cutover to the new data center, with seamless failover from the disaster recovery site.
- Decommissioning of the old data center, including secure data erasure and equipment disposal.
- Post-Relocation Activities:
- Post-implementation review to identify lessons learned and best practices.
- Final project documentation.
4. Deliverables:
- Fully operational data center at the new location.
- 100% client uptime throughout the relocation process.
- Decommissioned old data center.
- Complete project documentation, including:
- Project plan
- Test plans and results
- Cutover plan
- Post-implementation review
5. Timeline:
- Project Start: April 15, 2024
- Project End: September 15, 2024 (estimated)
- Detailed milestones and task dependencies will be defined in the project plan.
6. Budget:
- $90,000 - $100,000 (inclusive of new site infrastructure upgrade)
7. Responsibilities:
- Charles Parker (Project Manager): Overall project management, coordination, and communication.
- Project Team Members: Execution of assigned tasks, reporting progress, and escalating issues.
- Marion Hassing (Project Sponsor): Providing overall direction, approving key decisions, and ensuring resource availability.
8. Acceptance Criteria:
- Successful cutover to the new data center with zero client downtime.
- All systems functioning as expected at the new location.
- Completion of all project deliverables.
- Project completion within the agreed-upon timeline and budget.
Project Charter: Future Technology Data Center Relocation
Project Name: FT Data Center Relocation
Project Sponsor: Marion Hassing, Vice President of Operations
Project Manager: Charles Parker, Network Administrator
Date: May 1, 2024
1. Project Goals:
- Relocate the Future Technology data center from its current location at 4th Floor, Old School Building, Downtown Mobile, AL to the new facility at Mobile International Airport Industrial Complex.
- Maintain 100% uptime for all 315 FT clients during the entire relocation process.
- Complete the relocation within a four to five-month timeframe.
- Stay within the estimated budget of $90,000 - $100,000.
2. Project Scope:
- This project encompasses all aspects of the data center relocation, including:
- Physical relocation of all hardware and software.
- Infrastructure upgrade and installation at the new site.
- Testing and validation of all systems at the new location.
- Coordination with the remote disaster recovery "hot" site for seamless failover during the transition.
- Decommissioning of the old data center.
- This project excludes:
- Enhancements or upgrades to existing hardware or software beyond what is necessary for the relocation.
- Training for FT staff on new systems (if any).
3. Key Deliverables:
- Fully functional data center at the new location.
- 100% uptime maintained for all clients throughout the relocation.
- Decommissioned old data center.
- Project documentation, including lessons learned.