A wind power farm in the North Sea outside of Denmark consists of 10 wind power plants in which each wind power plant has an installed power of 1 MW. During one week in February 2017, major maintenance work was being carried out on half of the wind power plants, resulting in a situation in which 50% of the wind power plants were delivering energy at 50% of their installed power during the week. The rest of the wind power plants continued to deliver energy at full capacity during the week, i.e., at 100% of their installed power.

What was the installed power of the wind power farm that week?

What was the degree of utilization of the wind power farm during that week?

 

 

 

This question has been answered.

Get Answer