National Oceanic Research Institute

The National Oceanic Research Institute is planning a research study on global warming in Antarctica. The major tasks and their durations and precedent activities are shown in Table 1 below. The Table also shows the budget expenditures of each activity. For example, activity A, preliminary plan, costs $3,000 and lasts for 3 weeks, such that, each week, the cost is $1,000. On the other hand, activity I, additional equipment, costs $20,000, lasts for 3 weeks, but $10,000 needs to be paid in the first week while $5,000 is paid in the second and third week .

Solve all the questions using Excel

Part 1 (time Planning)
1- Use Excel to develop
a. Gantt chart
b. AoN network
c. Use the AoN calculation to find the total and free slacks. (please summarize your answer in a table format)
2- Use project plan 360 to confirm your Excel calculations
Part 2(resource planning)
1- Use Excel to develop resource histogram for each resource
2- Use project plan 360 to develop a resource histogra
Part 3(EVM)
Use Excel only for the required calculations

Q1 Scheduling:

 Calculate the project minimum duration.
 Calculate the slack time of each activity.
 Identify the critical path(s).

Q2 Costing:

 Develop a time-cost curve for the above project

Q3 Earned value management

 At the end of week 6, information about the project was collected as shown in Table 2. Calculate the missing information in the table: Earned Value (EV), Planned Value (PV) of each activity, Cost Variance (CV), and Schedule Variance (SV).
 Calculate the Cost Performance Index (CPI) and Schedule Performance Index (SPI).
 Predict the Estimated Cost at Completion (EAC) and the project expected duration.

Sample Solution